PROJECT TIMELINE
January - March 2024 Preliminary Design
*
January 16-Start up meeting with District Officials
Reviewed: Drawings, Field Work, Scope, Timeline, and Construction Manager/Clerk Works.
*
February 16
Bid Opening Construction Management Team
Review Project Status and Entry Designs
* March 25
30% meeting-Architect & Construction Manager added into our meeting. Looked at 2 designs for front of building and discussed next steps including finalizing front design, permits and tests needed as well as upcoming deadlines.
BOE Update 4/17/24
Option 1 Option 2
*May 1
July 2024 SED Submission
*Earlier Date than originally projected*
January 2025
SED APPROVAL
February 2025
Bid Opening
April 2025
Contract Award
June 2025
Site Mobilization
September 2026
Substantial Completion
PROJECT OVERVIEW
PROJECT FINANCIALS
INFORMATIONAL FLYER
PROJECT PRESENTATION
IMPORTANT DATES
11/27/23 Information Session Big Moose Fire Station 7pm
11/29/23 Information Session Woodgate Library 7pm
12/6/2023 Public Hearing Cafeteria 7pm
12/7/2023 Voter Registration Library Hallway 4-8pm
12/13/23 Vote Gymnasium 2pm-8pm